Week 4 Progress

  In the last few days the floor has been grouted in the new restaurant and the two private offices at the far end of the building have been plastered. The reception counter has started to take shape and the cable has been put in so that we can operate the barrier and the swimming pool door from our new reception office. The work continues…


Week 3 Progress…

The start of week 3 has seen the underfloor heating go in, the concrete base for the new floor being laid and the new reception entrance begin to take shape. Both the plumbers and electricians have started their work, and we are now seeing real progress being made. Exciting times indeed…    


New Reception & Restaurant- Week 2

Week 2 and we have already seen the removal of most of the old fixtures, with the framework for the new offices and restaurant in place. We have decided to increase the size of our farm shop and this will now occupy the space which was the games room, a new games room will be introduced as we progress. Alongside our offices and farm shop we will have brand new toilets installed also. Our new…


Out With The Old and In With The New- Week 1!

We have today began the total transformation of what was our old restaurant and games room, into what will soon be our brand new purpose built reception,restaurant, offices, lounge area and farm shop. Attached below are some images of what it was like,and  as we progress we will post more so you can enjoy seeing the transformation as it happens.


New Year 2016

What a fantastic evening we had in the Crowtrees Inn to see off 2016, starting off with over 110 owners and guests enjoying the truly wonderful food Andy and his team served up, to the dulcet tones of Dave Pinder-Gibb giving us all a memorable evening of music and song to round off a perfect night. Huge thanks again to all the staff involved in making the occasion a great success, and to all our…